Aims for January opening; work continues on Uptown water main
The city of Sedona stands by the safety of the Uptown Parking Garage’s concrete, Interim City Manager Kevin Phelps wrote in a Nov. 18 memo to the Sedona City Council.
“The UPG was built to the technical specifications called for by the project architect,” he wrote. “Further, it will show that the manner in which the city’s quality control procedures were put into place were consistent with good construction oversite [sic].” Phelps wrote the memo in response to “safety assertions expressed recently by several residents” about the compressive strength of the UPG’s concrete at Oct. 27 and Nov. 10 council meetings.
On Oct. 27, council directed Phelps to address resident concerns about the concrete’s compressive strength.
Quality Testing LLC the city’s materials testing consultant – identified low strength numbers at the seven-day, 28-day and 56-day testing marks for concrete in the lower-level ramp walls on the garage’s east side, falling short of the the structural engineer’s 5,000 psi stan-dard, according to the memo.
However, “concrete continues to harden and gain strength over time, although most of the strength is devel-oped in the first few weeks after placement,” according to the American Cement Association.
Follow-up tests by Quality Testing and concrete subcontractor Martin Marietta were independently done and Quality Testing’s “new strength test indicated improved strength numbers indicating approximately 4,700 psi,” while Martin Marietta’s “strength numbers came in slightly above 5000 psi,” the memo reads. The project’s structural engineer determined those measure-ments were within design standards, according to the memo.
Water Main
On Oct. 27, council approved a $3.95 million agree-ment with Arizona Water Co. to install a new 16-inch water main to improve the water velocity to the garage and the structure’s fire suppression system. The second phase of the agreement will replace the main along Van Deren Road from Forest Road to Schnebly Road.
The project is currently moving ahead “the contractor has begun doing core sampling,” Phelps said.
Phelps said he did not have a definitive date for the garage’s opening because he is currently making a punch list of final items for the project, but the target opening remains the end of January.
Employee Parking Plan
Council is scheduled to discuss parking options and possible adoption of the Uptown Parking Plan on Tuesday, Nov. 24, after press time.
The original plan would cluster a majority of about 200 employee spaces on the north end at parking lot 5.
“We’re going to have, I would say, close to a 55%-45% split between available employee parking on the north end versus the south end.”
Potentially that ratio can be reached at the Uptown Parking Garage and Lot 5, according to Phelps.
“We’ve checked with our technology company,” he said. “We’re going to be able to adapt the technology so that people can park on the roof, and we can have a way to manage that. We’ve looked at Lot 5, and we’ve got a design for how we can bifurcate Lot 5 to have both a visitor and employee component.
“Staff did a great job. They actually came up with a design where can easily move some bollards, so we could make either the employee lot about 30 spaces larger, or we could make the capacity increase for the customers by about 30 just by moving a set of bollards. So… we’ve got some flexibility of how we do that.”