Council grants Saddlerock 2-year extension3 min read

The Village at Saddlerock Crossing is a 100-unit hotel with 46 workforce apartments in five buildings across 6.36 acres planned for 1259 W. State Route 89A. The Sedona City Council voted 4-3 to approve a zone change for the site on Sept. 24, 2024. Baney Corp. asked for a two-year extension on Tuesday, Sept. 8. Map courtesy of Stephen Thompson Architect

The Baney Corp.‘s Village at Saddlerock Crossing project will have another two years to build its 100-room hotel now known as the Darling Hotel and 46 multifamily housing units on 6.36 acres at 1259 State Route 89A.

The Sedona City Council approved the extension 6-1 on Tuesday, Sept. 8, with Councilwoman Kathy Kinsella opposed.

The city and Baney said the extension was necessary because the Land Development Code’s Section 8.3.H(3) requires construction to begin within two years of a project’s initial approval.

“I was in favor of the project due to the community benefit that I see from the project and the work that I thought that they did through all the public meetings [that] I sat through with the people who live behind them, to try and meet the criterion and demands and requests from that group, so I supported it then, and I don’t see any reason not to give them the extension,” Councilwoman Melissa Dunn said.

“I’m opposed to this extension because I have had concerns for the last 10 years about this project that’s been going that long since it first came about and was introduced,” Kinsella said. “I think here we are all this time later, and there’s still not a resolution to things that I think should have been worked out years ago. So I don’t have a lot of confidence, and therefore I’m going to oppose the extension.”

Council voted 4-3 on Sept. 24, 2024, to approve the zone change of the former Biddle Outdoor Center nursery on Soldier Pass Road with Kinsella, then-Mayor Scott Jablow and then-Vice Mayor and current Interim Mayor Holli Ploog opposed.

Advertisement

At its meeting Aug. 4, the Sedona Planning and Zoning Commission unanimously recommended the extension.

The extension request was submitted on June 24, after the Baneys submitted building permits for the grading and multifamily portions of the project in March and the Darling Hotel in April. Comments were provided on June 8, and the grading and housing permits were resubmitted on Aug. 13. The review is anticipated to be completed soon.

“I voted against the project, but I’m going to support this extension,” Ploog said. “But I’m only going to support for another two years, because I think that should be sufficient time to get grading done and buildings constructed and as long as you have assured us that everything’s in place and you’re just waiting for getting approval on your permits. I wish you success and just keep it moving because it is kind of an eyesore for 10 years, we like to see something there.”

“When we brought this before the council two years ago, there were a number of items that staff had identified as deficient related to the LDC,” said the corporation’s attorney, Benjamin Tate. “So, if I’m being candid, we were so focused at the time on simply getting the project approved that we hadn’t considered the fact that two years may not be enough time to get us all the way to permits because of addressing these issues.”

“I think conceivably we could be started after the first of the year by the time we get building permits and get staged and ready for construction,” said Curt Baney, president and CEO of the Baney Corporation.

The Darling Hotel name comes from the middle name of the daughter of “heir apparent” to the company, Hayden Baney, according to Tate.

Oak Creek Water Co. is currently using the development’s lot as a construction staging area for infrastructure improvements in the neighborhoods between 89A and Airport Mesa.

“That is a month-to-month lease,” Baney said. “So as soon as we get our building permit and are ready to start construction, if it’s less than nine months, they’ll be asked to move, locate somewhere else.”

Joseph K Giddens

Joseph K. Giddens grew up in southern Arizona and studied natural resources at the University of Arizona. He later joined the National Park Service in many different roles focusing on geoscience education throughout the West. Drawn to deep time and ancient landscapes he’s worked at: Dinosaur National Monument, Petrified Forest National Park, Badlands National Park and Saguaro National Park among several other public land sites. Prior to joining Sedona Red Rock News, he worked for several Tucson outlets as well as the Williams-Grand Canyon News and the Navajo-Hopi Observer. He frequently is reading historic issues of the Tombstone Epitaph newspaper and daydreaming about rockhounding. Contact him at jgiddens@larsonnewspapers.com or (928) 282-7795 ext. 122.