Sometime between 5 p.m. and 7:30 p.m. the night of Tuesday Aug. 4, the SR179 Sewer Main Replacement Project suffered a sewage spill of 15,000 gallons to 20,000 gallons of “untreated liquid effluent” along State Route 179 near the Hillside shopping center, according to a press release from the city of Sedona.
The press release about the spill was issued at 6:12 p.m., Aug. 5, roughly 24 hours after the incident.
The SR179 Sewer Main Replacement Project is currently under construction from the Schnebly Hill Road roundabout to Hillside Sedona.
Residents and passersby reported untreated liquid effluent coming out of a manhole in front of the Hillside Sedona shopping center and flowing into a storm drain which then drained into Oak Creek approximately 750 feet downstream from the State Route 179 bridge over Oak Creek.
City officials is estimated that approximately 15,000 gallons to 20,000 gallons of untreated liquid effluent spilled into Oak Creek.
The spill was contained and disinfected around 8:30 p.m. that same evening. Kinney Construction Services, the contractor for the construction project, is responsible for this accidental spill.
For context, the volume of effluent translates to approximately 150 gallons per minute. For comparison, Oak Creek’s rate of flow is 13,000 gallons per minute.
The immediately affected areas of the creek have been cordoned off with yellow caution tape.
The city of Sedona and Kinney Construction Services have commenced water quality tests both upstream and downstream of the spill area. Soil tests will be taken in the spill vicinity.
The city of Sedona expects to receive test results in approximately 24 hours that will be sent to the Arizona Department of Environmental Quality, city officials stated.
In the statement, the city will continue working closely with ADEQ to develop additional steps that may be needed to remediate the spill.
Kinney Construction Services is hand-delivering information on this spill to residents and business with direct creek access located downstream from the spill, city officials stated. Other public notices have been placed at trailheads and areas where people frequently access Oak Creek.
As a result of this incident, work has been temporarily suspended as the contractor develops a plan to ensure that a spill does not occur again and to safely continue moving forward with the utility installation project, city officials stated. The contractor will continue to make every attempt to complete work along State Route 179 as soon as possible.
The city will continue to keep the community informed as new information becomes available.
For project information, including an FAQ on this incident, please visit www.sr179sewermainreplacement.com. To contact a project team member with questions regarding this event, email news@sr179sewermainreplacement.com or call the Project Hotline at (928) 852-4164.

City of Sedona Sewage Spill FAQs
This document will be updated as new information is available. Last updated: 8-5-20
What happened?
Sometime between 5 p.m. and 7:30 p.m. the night of August 4, 2020 a sewage spill occurred along SR179 associated with the SR179 Sewer Main Replacement Project that is currently under construction. The spill was contained and disinfected around 8:30 p.m. that same evening. Kinney Construction Services, the contractor for the construction project, is responsible for this accidental spill. Untreated liquid effluent was reported coming out of a manhole in front of the Hillside Sedona Shopping Center and flowed into a storm drain which then drained into Oak Creek approximately 750 feet downstream from the SR179 bridge over Oak Creek. At this time, it is estimated that approximately 15,000 to 20,000 gallons of effluent spilled into the creek. For context, the approximate volume of effluent translates to approximately 150 gallons per minute. It is estimated that 13,000 gallons per minute flow down Oak Creek.
Did solid waste and toilet paper flow into Oak Creek?
No, solid waste and toilet paper did not flow into Oak Creek. Only liquid effluent spilled into Oak Creek.
Is it safe to swim?
The City is waiting for water quality test results upstream and downstream from the spill to understand the effects. Out of caution, it is advised that pets and people do not swim in Oak Creek downstream from the spill until test results come back. Swimming areas like Crescent Moon have been notified.
Is there a risk to get COVID-19 from exposure to Oak Creek?
No, there is extremely minimal risk of getting COVID-19 from this spill into Oak Creek.
Will this push the timeline for the project back?
Most likely. As a result of this incident, work has been temporarily suspended as the contractor develops a plan to ensure that a spill does not occur again and to safely continue moving forward with the project. The contractor will continue to make every attempt to complete work along SR179 as soon as possible.
How are you notifying people?
The contractor for the 179 Sewer Main Replacement Project is hand-delivering information to all downstream properties proximate from the spill. The City posted information to social media and sent out a press release to all local media and anyone signed up to receive the City’s news alerts. Forest Service crews helped to place signs at trails and other locations where people often access Oak Creek. Additionally, anyone signed up to receive updates on the specific project was sent an email.
How do I sign up for updates on this project?
Subscribe to email updates by sending an email to news@sr179sewermainreplacement.com.
Who can I talk to for more information?
You may call the project hotline at (928) 852-4164 or send an email to news@sr179sewermainreplacement.com