The Sedona City Council voted unanimously to spend more than $4 million for needed capacity upgrades to the Sedona Wastewater Reclamation Plant.
The vote came during the Nov. 12 council meeting.
According to a report, staff was requesting approval of a construction contract with Phoenix-based Currier Construction Inc., in the amount of $4,271,789, for construction of the treatment plant upgrades. The work includes a base bid amount of $2,939,959 for construction of a secondary clarifier, new aeration blowers and associated electrical and instrumentation components.
The bid alternate, in the amount of $1,331,830, is for the construction of a new sludge digester, digester blowers and associated electrical and instrumentation components, a report states. The funding for this project is budgeted in the five-year Capital Improvement Plan and will span two fiscal years. The construction of the bid alternate is scheduled for fiscal year 2016. However, City Engineer Andy Dickey said based on engineer’s estimates, constructing the bid alternate at the same time as the base bid will result in more than $500,000 in savings. Therefore, award of the bid alternate was being recommended.
To read the full story, see the Wednesday, Nov. 19, edition of the Sedona Red Rock News.