City OKs flood drainage design

The city of Sedona improved a drainage improvement design for Brewer Road/Tlaquepaque.

History has shown that the area around Tlaquepaque is one of many in town that is prone to mass flooding.

As a way to help mitigate this problem, the Sedona City Council approved a contract for the Brewer Road/Tlaquepaque drainage improvement design Sept. 8 with Shephard-Wesnitzer Inc. in the amount of $153,855.

According to a city document, during the council meeting held on Feb. 26, 2013, the Soldier Wash Interim Improvements Study — completed by Shephard-Wesnitzer — was reviewed and approved moving forward with the recommended Alternates 1 and 2 of that study. At that time, staff recommended delaying Alternate 3 until a design for the 25-year flow capacity could be completed.

  • Alternate 1 included removing the existing obstructions at the channel banks to increase the flow area. The majority of this work is complete.
  • Alternate 2 included constructing walls near the top of the wash banks to increase channel capacity and reduce flooding over the banks. The Soldier Wash Jersey Barrier Project completed a portion of this work.
  • Alternate 3 included removing the existing double box culverts at Portal Lane as well as the removal of the pedestrian walkway between the Tlaquepaque and Los Abrigados properties and replacing them with clear span bridge crossings, and removing/replacing bank stabilization to increase channel flow area.