ADOT expects to finish work on State Route 179 by early June at the latest
The delays and backups motorists have been experiencing on State Route 179 for more than two years will soon be a thing of the past, the Arizona Department of Transportation reported.
The State Route 179 construction project, that begin in February 2008, is nearing its final stages and is still expected to be completed in late May or early June.
Carl Burkhalter, ADOT project manager, said the bridge and walls near Canyon Drive are the biggest parts of the project still needing to be completed.
As ADOT crews work on the walls, traffic backups have increased during the morning and evening hours, especially near Canyon Drive.
He said crews are working on both walls at opposite sides of the roadway and called this one of the last major components of the project.
ADOT is hoping to complete both walls and the bridge by the end of April before beginning the final touches and cleanup, which includes some landscaping.
Once the walls and bridge are completed, the road would need to be repaved with one-half inch rubber asphalt and striped before ADOT goes over a punch list to make sure everything was done correctly and nothing was missed.
The final striping, scheduled for June, would probably be done during the night.
Burkhalter said the recent rains did slow ADOT down. He said crews worked hard to ensure their work was not wiped out by the possibility the Oak Creek Canyon could crest and spill onto State Route 179.
He said doing this took valuable time away from working on the project. He added the amount of rain also did not help the time line.
Burkhalter said the biggest and most time consuming part of the project has been completed.
“The good news is the bridge is out of the creek,” he said.
He said ADOT will also work on the roundabouts at both Schnebly and Canyon roads sometime in May.
Burkhalter said the one-half inch rubberized asphalt for the streets cannot be put down until the weather changes, and he is hoping this portion of the project will begin Thursday, April 15.
The rubberized paving requires temperatures to be at least 85 degrees in order for the asphalt to cure, and ADOT thinks the anticipated completion date for laying the asphalt will be within two weeks from the start date.
Burkhalter stressed the road will always remain open for traffic, and if traffic is going to be impacted to a large degree, crews work at night.
He said ADOT’s night work at this time consists of putting up the storm drain at Canyon Drive and Morgan Wash.